Water District Says Lehigh Quarry Pit May Play Role in Flood Protection Plan

Permanente Creek flood control designs altered downstream in Mountain View.

A Quarry pit could be the answer to a controversial flood control project along Permanente Creek in Los Altos and Mountian View, Santa Clara Valley Water District (SCVWD) spokespersons said yesterday.

Originally the district planned a 21-foot deep water detention basin at Cuesta Park Annex, which was hotly debated by residents in Mountain View. 

Now district officials say they may not have to dig as deep, or they may be able to take a different approach eliminating the need for the basin.

"We've done some new hydrology studies and discovered that some of the flow that we thought went into Permanente Creek actually flows in Lehigh Southwest Cement quarry pits," said SCVWD spokesman Marty Grimes. "That means we don't have to go the same depth."

Instead, according to Grimes, the water district project managers will present two alternative project proposals to the water district Board of Directors, and in October, to the Mountain View City Council.

Find out what's happening in Cupertinowith free, real-time updates from Patch.

One proposal calls for a smaller 11-foot basin at the Cuesta Park Annex site "that would provide the same flood protection," said Grimes.

The other plan builds a pipe under Cuesta Drive that catches the storm water and diverts it from Permanente Creek.

However, with the latter proposal there may be some "parcels upstream of Cuesta Park that would not be protected; that includes El Camino Hospital," he said. To mitigate flooding upstream, the water district plans to either deepen or widen Hale Creek, which runs through Los Altos and Los Altos Hills.

The Permanente Creek Flood Protection Project sprung from a bond measure in 2000 that created funds for the water district to help protect 1,664 homes from the probability of a 100-year flood. The project included the original proposal for the 21-foot basin at the Cuesta Park Annex location, one at McKelvey Park, one at Rancho San Antonio and another at Blach Intermediate School in Los Altos.

, however, they had to find alternatives. One of those may have been to build a dam, according to Afshin Rouhani, project manager.

"When all the other options failed, the possibility of a dam came up," Rouhani said. "But there are significant environmental impacts."

However, with the discovery that water had been diverted to the pits at the Lehigh Cement quarry, "a dam is no longer necessary," Rouhani said.

The water district estimated that the original 21-foot basin at Cuesta Park Annex would cost $40 million. That would remain the price tag for the 11-foot basin since the structural modifications to Hale Creek would still need to be made. The alternate scenario, the laying of the water catchment pipe beneath Cuestra Drive, sheds $6 million from the cost. These plans still include the changes at Hale Creek.

Find out what's happening in Cupertinowith free, real-time updates from Patch.


Get more local news delivered straight to your inbox. Sign up for free Patch newsletters and alerts.

We’ve removed the ability to reply as we work to make improvements. Learn more here